Combo update, Fri,Sat,Mon. Fri. Finished up mounting the center stack trays and the centerstack sub-panel. I test fit the panel |
|
and found that I had some interferrence w/ the JPI EIU and the Copilot EFIS. So I moved the JPI EIU to the forward side of the |
|
instrument subpanel. I figured out which cables from the JPI need to be passed forward thru the firewall, and routed them. then I |
|
finished up sealing the EPM Stainless Steel firewall passthru. On Saturday John Cox was here for a n EAA tech councilor review |
|
of my project. He identified several things forward of the firewall that could be improved. One was the cyl head baffles were |
|
rubbing directly on the heads. I removed the tension rods, and applied a bead of red RTV to the fwd and aft baffles on each side. |
|
I'll let this set up overnight and then resecure. so that tomorrow i'll be able to connect the CHT harness to the probes. I replaced |
|
the cotter keys on the engine mount with stainless steel. Added 5 more adel clamps to further secure some of the hoses. Also |
|
shortened the Manifold Pressure hose. I don't know why Van's has these hoses so long. I picked up a mandrel from Aerozona |
|
parts this am. I was reluctant to make any of my own hoses, but after remaking this one, its really not a big deal. Tomorrow I'm |
|
tackeling the EGT & CHT harness. i've been reluctant to do this as I want a neat/tidy engine compartment, and I'm afraid I'll |
|
screw up and get one of the probes too short. I cut a section off one of the harness leads and did a dry run test of one of the |
|
|